Albuquerque (March 9, 2012) – Traffic Report

This report replaces previous report.

I_40 Reconstruction Project / Mile marker 140 to 146, From Rio Puerco east approx. 6 miles (Mountain States Constructors /Tim Chavez PM) Completion date 10.24.12

· Ongoing and until further notice- I_40 westbound from mile marker 146 to 140 will be reduced to one lane during project.

N_M 6 Curb & Gutter w/Sidewalk / from Los Cerritos to Los Lentes, (G Sandoval Const. /Justin Gibson PM) Completion date 5.4.12

· Ongoing and until further notice – N_M 6 from Los Cerritos to Los Lentes will have activity on the shoulders with occasional right lane closures for curb & gutter/sidewalk installation. Use caution and reduce your speed through the work zone.

N_M 5_28 (Alameda) Paving Project / San Pedro to Edith (FNF / Tim Chavez) 30 calendar Day Project

· Suspended

I_25 Paving Project / Mile marker 174.8 to 187, South of Belen to Southern District 3 Boundary (Hamilton /Gibson) 180 work Day Project

· Ongoing and until further notice (Hamilton Construction)- I_25 both directions from mile marker 174.8 to 187 will have various lane closures in 2 mile increments for roadway rehabilitation. Established lane closures will remain during overnight hours. Use caution and reduce your speed.

I_25 Fencing Project / Mile marker 213.6 to 220.4 /Rio Bravo to Broadway (Kimo Constructors/ Jay Loomis) 45 Calendar Day Project

· Monday 3/12 through Monday 4/16 from 7am to 6pm each weekday – I_25 both directions between Rio Bravo and the Broadway exit (213.6 to 220.4) will have activity in the median during this project.

DISTRICT WIDE TRAFFIC IMPACTS

Sunday 3/11 through Thursday 3/29 from 8pm to 5:30am each Sunday through Thursday evening (Hayward Baker/Dodge) – I_40 both directions over Public School Road at mile marker 174 (between Carnuel and Tijeras) will have various lane closures for bridge approach maintenance. Work will initiate in the westbound direction before moving to eastbound. Expect minor delays, reduce your speed and use caution through the work zone.

Tuesday 3/13 through Thursday 3/15 from 9am to 3pm (NM Gas Co.) – N_M 45 (Coors) southbound between Phillips Drive and Coors Place will have the right lane closed for utility work.

Ongoing through Friday 3/16 from 8am to 5:30pm each weekday (G. Sandoval Const.) – N_M 6 eastbound from mile marker 28.75 to 31 (just west of Jubilee) will have intermittent closures for driveway installation. Flagmen will be onsite to move traffic through the work zone.

Ongoing through Friday 3/30 from 7am to 6pm each weekday (Qualcon) – I_25 both directions at mile marker 175.5 (Bernardo) will have various single lane closures for bridge deck maintenance.

Ongoing through Friday 4/20 from 7am to 7pm (RMCI/TOWN OF BERALILLO) – N_M 3_13 both directions from Calle Del Norte to U_S 5_50 will have various lane closures for streetscape project.

· Ongoing through Monday 7/16 from 7am to 3:30pm each weekday (Lee Landscapes.) – I_40 both directions from Coors to Unser will have activity in the median during landscaping project. Be alert for turning trucks into and out of the work zone.

Ongoing through Wednesday 10/3 from 9am to 3:30pm each weekday and from 8:30pm to 5:30am each weeknight (Village of Corrales) – N_M 4_48 (Corrales Road) from Alameda to Meadowlark will have utility installation on the shoulders and various lane closures. Expect delays!

All projects scheduled weather permitting and are subject to change without notice. For more information please contact, Phil Gallegos, NM Department of Transportation at 798-6645 or 220-4153, logon to www.nmroads.com. or dial 511.

Phil Gallegos

NMDOT DISTRICT 3

PUBLIC INFO OFFICER

505-798-6645 OFFICE

505-220-4153 CELL